Sr.no. |
Category Type |
Proof required |
1 |
For Off-Grid CPP |
Certification from concerned Distribution Licensee /
Transmission Licensee (as per case may be)
|
2 |
For Grid connected CPP having Co-generation facility |
Certification from concerned Distribution Licensee /
Transmission Licensee/ Electrical Inspector, PWD,
GoM/ MPCB / MEDA.
|
3 |
For CPP in case of Standby (or Emergency Back-up) Captive Generating Plant facilities. |
Certification from concerned Distribution Licensee /
Electrical Inspector, PWD, GoM.
|
4 |
For renewable based CPP/ OA consumers |
Certification from MEDA.
|
5 |
In case of OA consumers |
Certification from concerned Distribution Licensee /
Transmission Licensee (Valid OA permission)
|
6 |
In case of CPP generating plant is Shut down / Un-operational / Company is Lock down. |
Certification from Electrical Inspector, PWD, GoM.
|
7 |
Having capacity less than 1MW in case of CPP or having contract demand less than 1MVA in case of OA consumer |
Commissioning certificate / Grid connectivity certificate from concerned Distribution Licensee / Transmission Licensee or Registration certificate from office of Electrical Inspector
|